R.E.News future Technology-Buildots unveils AI-powered forecasting tool to mitigate delays

Njc 34 30/05/24-FR-English-NL-footer

Buildots dévoile un outil de prévision basé sur l'IA pour atténuer les retards

20240513 130951 buildotsdelay forecastBuildots says that it developed this feature after conducting research that found 62% of construction site activities consistently run slower than planned (Photo: Buildots)

Buildots, une entreprise de technologie de construction d'IA, a récemment lancé sa dernière fonctionnalité appelée « Delay Forecast ».

L'outil basé sur l'IA prédit les risques de retard et alerte les équipes de construction des problèmes potentiels de rythme, leur permettant ainsi de prendre des mesures proactives pour atténuer les retards potentiels avant qu'ils ne s'aggravent.

De plus, la fonctionnalité fournit une analyse granulaire au niveau de l'activité de la cause première des retards qui aide les chefs de projet à améliorer continuellement les performances et la stratégie.

La fonctionnalité Delay Forecast est intuitivement intégrée au tableau de bord principal de Buildots et signale les activités qui risquent de prendre du retard.

Il quantifie ces risques grâce à des projections de retards prévus, ainsi que des recommandations de corrections de rythme afin d'éviter les retards. Lorsque les utilisateurs reçoivent des alertes de retard, ils peuvent saisir de nouvelles hypothèses de rythme et voir comment ces changements pourraient affecter la chronologie, ce qui leur permet d'optimiser et d'affiner les stratégies et de déterminer la meilleure voie à suivre.

Le tableau de bord permet également aux équipes de projet de suivre les tendances des risques semaine après semaine, leur permettant ainsi de voir l'impact réel de leurs décisions.

Buildots affirme avoir développé cette fonctionnalité après avoir mené des recherches qui ont révélé que 62 % des activités des chantiers de construction se déroulent systématiquement plus lentement que prévu, et 25 % s'exécutent à la moitié de leur rythme prévu.

La recherche a également révélé que, bien souvent, les activités critiques se déroulaient mal, semaine après semaine, et que ces problèmes passaient inaperçus jusqu'à ce qu'ils aient déjà eu un impact significatif sur les délais des projets.

« Chez Buildots, nous pensons que des données d'avancement précises, des indicateurs de performance et des informations basées sur les données sont essentiels pour résoudre les problèmes qui affectent presque tous les projets de construction, tels que les retards et l'inefficacité », a déclaré Aviv Leibovici, co-fondateur et CPO de Buildots.

« Ces convictions fondamentales inspirent tout ce que nous faisons, du développement de la méthode de gestion de construction axée sur la performance (PDCM) à la conception de nouveaux outils comme Delay Forecast. »

La nouvelle fonctionnalité aurait été testée en version bêta sur un certain nombre de chantiers de construction dans le monde et il a été démontré qu'elle permettait une réduction de 50 % des temps de retard lorsqu'elle était utilisée avec la méthode PDCM.

L'un de ces sites est un complexe gouvernemental danois à grande échelle, actuellement en construction par le principal entrepreneur scandinave NCC Denmark.

Selon le chef de projet Niels Frank Jensen, « Grâce à Delay Forecast, nous pouvons non seulement identifier les risques très tôt, mais également informer nos métiers du rythme exact requis pour respecter le calendrier. Les métiers peuvent ajuster les ressources en main-d'œuvre en conséquence en visualisant les quantités de travail. Nous sommes enfin capables de suivre notre instinct et de prioriser les activités en fonction des performances réelles et de ce qui est réellement à risque.
NJC.© Info Buildots

----------------------------------------------------------------------------------------------------------------

Njc 34 30/05/24-English

Buildots unveils AI-powered forecasting tool to mitigate delays

20240513 130951 buildotsdelay forecastBuildots says that it developed this feature after conducting research that found 62% of construction site activities consistently run slower than planned (Photo: Buildots)

Buildots, an AI construction technology company, has recently launched its latest feature called ‘Delay Forecast’.

The AI-powered tool predicts delay risks and alerts construction teams about potential pace issues, allowing them to take proactive measures to mitigate potential delays before they escalate.

Additionally, the feature provides a granular, activity-level analysis of the root cause of delays that helps project managers improve performance and strategy continually.

The Delay Forecast feature is intuitively integrated into Buildots’ main dashboard and flags activities that are at risk of falling behind schedule.

It quantifies those risks through projections of predicted delays, as well as providing recommendations for pace corrections to prevent delays. When users get delay alerts, they can input new pace assumptions and see how these changes might affect the timeline, allowing them to optimise and fine-tune strategies and determine the best path forward.

The dashboard also enables project teams to track risk trends week by week, allowing them to see the real-life impact of their decisions.

Buildots says that it developed this feature after conducting research that found 62% of construction site activities consistently run slower than planned, and 25% run at half their planned pace.

The research also revealed that many times, critical activities performed poorly week after week, and these issues go unnoticed until they have already significantly impacted project timelines.

“At Buildots we believe that accurate progress data, performance indicators, and data-driven insights are critical to solving issues that plague almost all construction projects, such as delays and inefficiency,” said Aviv Leibovici, co-founder and CPO of Buildots.

“Those core beliefs inspire all that we do, from developing the Performance Driven Construction Management (PDCM) method, to designing new tools like Delay Forecast.”

The new feature is said to have been beta-tested on a number of global construction sites and has been shown to facilitate a 50% reduction in delay times when used together with the PDCM method.

One of those sites is a large-scale Danish government complex, currently being built by leading Scandinavian contractor NCC Denmark.

According to project manager Niels Frank Jensen, “Using Delay Forecast, not only can we now identify risks very early, but also inform our trades of the exact pace required to meet the schedule. Trades can adjust manpower resources accordingly by viewing quantities of work. We’re finally able to back our instincts and prioritize activities based on actual performance and what’s really at risk.”
NJC.© Info Buildots

---------------------------------------------------------------------------------------------------------------

Njc 34 30/05/24-NL

Buildots onthult een AI-aangedreven voorspellingstool om vertragingen te beperken

20240513 130951 buildotsdelay forecastBuildots says that it developed this feature after conducting research that found 62% of construction site activities consistently run slower than planned (Photo: Buildots)

Buildots, een AI-bouwtechnologiebedrijf, heeft onlangs zijn nieuwste functie gelanceerd genaamd ‘Delay Forecast’.

De AI-aangedreven tool voorspelt vertragingsrisico's en waarschuwt bouwteams over mogelijke tempoproblemen, waardoor ze proactieve maatregelen kunnen nemen om potentiële vertragingen te beperken voordat ze escaleren.

Bovendien biedt de functie een gedetailleerde analyse op activiteitenniveau van de hoofdoorzaak van vertragingen, waardoor projectmanagers de prestaties en strategie voortdurend kunnen verbeteren.

De functie Vertragingsprognose is intuïtief geïntegreerd in het hoofddashboard van Buildots en markeert activiteiten die het risico lopen achterop te raken op schema.

Het kwantificeert deze risico's door middel van projecties van voorspelde vertragingen, en geeft aanbevelingen voor tempocorrecties om vertragingen te voorkomen. Wanneer gebruikers vertragingswaarschuwingen ontvangen, kunnen ze nieuwe aannames over het tempo invoeren en zien hoe deze veranderingen de tijdlijn kunnen beïnvloeden, waardoor ze strategieën kunnen optimaliseren en verfijnen en het beste pad voorwaarts kunnen bepalen.

Het dashboard stelt projectteams ook in staat risicotrends week na week te volgen, zodat ze de werkelijke impact van hun beslissingen kunnen zien.

Buildots zegt dat het deze functie heeft ontwikkeld na onderzoek waaruit bleek dat 62% van de bouwplaatsactiviteiten consistent langzamer verloopt dan gepland, en 25% op de helft van het geplande tempo.

Uit het onderzoek bleek ook dat kritieke activiteiten vaak week na week slecht presteerden, en dat deze problemen onopgemerkt bleven totdat ze al een aanzienlijke impact hadden op de projecttijdlijnen.

“Bij Buildots zijn we van mening dat nauwkeurige voortgangsgegevens, prestatie-indicatoren en datagestuurde inzichten van cruciaal belang zijn voor het oplossen van problemen die bijna alle bouwprojecten teisteren, zoals vertragingen en inefficiëntie”, zegt Aviv Leibovici, medeoprichter en CPO van Buildots.

“Deze kernovertuigingen inspireren alles wat we doen, van het ontwikkelen van de Performance Driven Construction Management (PDCM)-methode tot het ontwerpen van nieuwe tools zoals Delay Forecast.”

De nieuwe functie zou in bètatesten zijn uitgevoerd op een aantal wereldwijde bouwlocaties en er is aangetoond dat deze een 50% reductie in vertragingstijden mogelijk maakt wanneer deze samen met de PDCM-methode wordt gebruikt.

Eén van die locaties is een grootschalig Deens overheidscomplex, dat momenteel wordt gebouwd door de toonaangevende Scandinavische aannemer NCC Denemarken.

Volgens projectmanager Niels Frank Jensen: “Met behulp van Delay Forecast kunnen we nu niet alleen risico's zeer vroeg identificeren, maar kunnen we onze transacties ook informeren over het exacte tempo dat nodig is om aan de planning te voldoen. Vakmensen kunnen de mankracht dienovereenkomstig aanpassen door de hoeveelheid werk te bekijken. We zijn eindelijk in staat om onze instincten te ondersteunen en prioriteiten te stellen aan activiteiten op basis van daadwerkelijke prestaties en wat werkelijk gevaar loopt.”
NJC.© Info Buildots

-----------------------------------------------------------------------------------------------------------------

Date de dernière mise à jour : 29/05/2024